Tramway Works Update 24.1.11

 

Added 24.1.11

 

Latest news below about the local tramway works in the Cleveleys, Anchorsholme, Fleetwood areas, from Lancashire County Council.

 

TRAMWAY UPGRADE WORKS

HIGHWAY CLOSURES – JANUARY 2011 ONWARDS

CLEVELEYS

Westmoreland Avenue

Further details to be advised

 

Cumberland Avenue

Carriageway to be closed across tramtrack commencing Monday 24th January. Temporary traffic diversion via  Westmoreland Avenue or West Drive.

 

West Drive

Further details to be advised.

 

York Avenue 

Current closure due to complete by early / mid February.

 

Victoria Square

Tramway to be upgraded through Victoria Square commencing early / mid February through to late April.  Traffic will not be able to travel across tram tracks.

Westbound traffic will be diverted via Crescent East and Crescent West, with traffic turning across tramway at Lauderdale Avenue.

Traffic which currently turns right from Crescent West into Victoria Road West will be diverted to cross tramway at York Avenue ( ie : north end of tram stops at Victoria Square ).

Traffic travelling north & south through Victoria Square will not be diverted – although there will be lane restrictions whilst works take place.

Pedestrians will cross tramtracks to north of Victoria Square ( between  Brighton Avenue & Rossall Road ).

 

ANCHORSHOLME  ( Blackpool Borough Council )

Anchorsholme Lane

Anchorsholme Lane will be closed to traffic crossing tramtrack for approximately two months, commencing mid February  ( i.e : on completion of works at Fleetwood Road ). 

 

Fleetwood Road.

Current closure due to complete by mid February. 

From this date traffic will be able to travel along full length of A587 both northbound & southbound.  The existing temporary diversion for southbound traffic via West Drive will no longer apply.

 

FLEETWOOD

 

Esplanade & Pharos Street

Carriageway remains closed - works currently due to continue until mid March.

 

North Albert Street

Carriageway remains closed – carriageway due to reopen to through traffic by end of February.  Construction of tram stops and pelican crossing  ( near library ) continues through into March.

 

Fishermans Walk – Lofthouse Way

Lofthouse Way – across tramtracks - due to be closed from Tuesday 25th January until mid March.

 

Radcliffe Road

Radcliffe Road / Copse Road tram crossing ( Near Stanley Road ).

Carriageway across tramtracks to be closed to upgrade tramway for approximately two months. These works will commence once works to tram crossing at Lofthouse Way have been completed. Date to be confirmed – but works not likely to commence prior to mid March.

 

Larkholme Lane

Carriageway across tram track due to close from mid February ( ie : on completion of current closure at Broadwater )

Broadwater

Fleetwood Road Tram Crossing will remain closed until mid February.  Fleetwood Road due to reopen mid February , with associated works ( Brook Street & new bus laybys to Fleetwood Road ) continuing into March

 

ROSSALL

 

South Strand

Carriageway closure across tramtrack due to start mid February . These works will commence once works to tram crossing at Rossall Lane have been completed. Temporary traffic diversion via Rossall Lane.

Rossall Lane

 

Current closure due to complete by mid February.

 

 

 

 

 

 

 

 

 

Advert navigation
Homepage
Shell
Youtube
facebook
Twitter
Subscribe to visitCleveleys and be the first to get updates, news, special offers, and find out what's happening!

Your details will only be used by visitCleveleys and not passed to third parties, in accordance with the Data Protection Act.
 
 
 
  ;